Monday, June 7, 2010

The microhydro plant


By Manfred Mornhinweg (manfred@ludens.cl)
My little paradise has a stream that provides enough water flow and head to run a small turbine, to provide electricity to my home. While writing this, the microhydro plant is being implemented, and here are some photos of the process.

Read more

Tuesday, June 1, 2010

Walsh River Micro-Hydro Turbine Contruction Guide

Prepared by Max Enfield, December 2007, revised March 2010

These notes are intended as a guide to those wishing the construct a Banki-crossflow turbine like that were previously available and used in the Walsh River Micro-Hydro Systems. The focus of the notes is on construction details, rather than design.

The Walsh River Micro-Hydro System derived its name from the Walsh River in Far North Queensland, where the prototype system was installed. The system concept was developed and prototyped in 1991 by Jerry Jeffress and features the integration of custom made Banki-crossflow turbines, with Baldor DC generators and AERL Hydromax DC:DC step down controllers. It can also be used to pump water, indeed it has been used to pump water and generate electricity simultaneously.

Read more



Friday, May 28, 2010

The head losses in the penstock





By Ahmad Suhendra
The various head losses which occur between reservoir and turbine are as follows:
1. Trashrack (or screen) losses
2. Entrance losses
3. Losses due to pipe friction
4. Bend losses
5. Losses in valve and fittings.
6. Losses in sudden contraction and expansion

Head loss due to installation of a trashrack

ht = [Kt* (t / b) ^ (4 / 3)* (Vo ^ 2 * Sin α)] / (2 * g)

Kt= depends upon the shape of the screen

Vo=Approach velocity (m/s)

Head loss due to entrance
he = Ke * V ^2 / (2 * g)

Ke = depends upon the shape of the intake opening
V = The average velocity of water in penstock

[Permissible velocity in Penstocks,V(m/s) =0.125 (2 g H)^0.5,
Ref : USBR (1961) (P J Bier)]


Head loss due to friction in the penstock
hf = [(10.29* n ^ 2 *Qp ^ 2) / Dp^5.333] *Lp
n = manning's roughness coefficient depends upon the type of pipe


Head loss due to the installation of the bend
hb= Kb * V^2 / (2 * g)

Kb= depends upon the shape of the bend and the condition

of the inside surface

V= The average velocity of water in penstock


Head loss due to Fitting and Valve
hv = Kv *V ^ 2 / (2 * g)
Kv= depends upon the type of fitting and valve

V= The average velocity of water in penstock



Head loss due to sudden contraction and expansion
hc = Kc *V ^ 2 / (2 * g)
Kc= depends upon the type of sudden contraction and expansion

V= The average velocity of water in small pipe
(1.273 Q /Dp^2 m/s)

Total Head Loss
h_total = ht + he + hf + hb + hv + hc
Where:

  • g = constant of gravity 9.8 m/s^2
  • Qp = flow in penstock (m^3/s)
  • Dp = inside diameter of penstock (m)
  • Lp= lenght of penstock (m)
  • k = resistance coefficient
  • t = screen thickness (mm)
  • b = width between bars (mm)
  • α = angle of inclination from horizontal (deg)
Ref:
  1. http://www.iaa.ncku.edu.tw/~aeromems/Mott/ch10.pdf
  2. ESHA (European Small Hydropower Association),”Layman’s Handbook on How To Develop a Small Hydro Site,”2nd ed, 1998


Thursday, May 27, 2010

Calculation of flood spillway

By Ahmad Suhendra
Flood spillway was designed based on the excess water and high water in the channel carrier (head race)

Example :
Flood Spillway will be made on a channel that has a water depth of 0.691 m, with a normal discharge (Q normal) of 0.6 m^3/sec. What is the length of Flood spillway?

Spillway length (L spillway) is obtained by using the equation of calculating Weir and must be able to pass through if the flow (Q spillway) in a state of excess but not based on the flood peak.

Dicharge Coefficient (Cd)
Profile of Crest Weir
μ- factor
Cd=2.953 μ
Board, sharp edge
0.49-0.51
1.44 - 1.51
Board, round edge
0.50-0.55
1.48 - 1.62
Round overfall
0.65-0.73
1.92 - 2.16
Sharp edge,
0.64
1.89
Rounded
0.75
2.21
Roof Shaped
0.79
2,33

Standard Weir equations:
Q = Cd * L weir * (h over the top )^1.5
In this case :
  • L spillway = L weir
  • Q spillway = Q minor flood - Q normal = Cd * L spillway * ( h over the top)^1.5
There are some values of  Discharge Coefficient  (Cd) and in this calculation the value of Cd was taken 1.6 (Board, the round edge)
Then :
  • L spillway = (Q minor flood – Q normal) / (Cd * ( h over the top)^1.5 )
To increase the water on the head race taken a number of around 20% of normal conditions and is considered as a minor flood (small flood).
  • Q minor flood = 1.2 * 0.6 = 0.72 m^3/sec
  • h minor flood = 1.2 * h = 1.2 x 0.691 = 0.829 m
  • h over the top = 0.829 - 0.691 = 0.138 m
  • Q spillway = 0.72 - 0.6 = 0.12 m3/sec
  • L spillway = ( 0.12) / (1.6 * 0.138 ^1.5) = 1.46 m


Thursday, May 20, 2010

Loss coefficients for pipe bends are commonly used in MHP

The losses in figure as shown left , vary according to the R/D ratio and the deflection angle of the bend. An R/D ratio of six results in the lowest head loss, although only a slight decrease is indicated for R/D ratios greater than four. As the fabrication cost of a bend increases with increasing radius and length, there appears to be no economic advantage in using R/D ratios greater than five.

Ref:
BURIED STEEL PENSTOCKS SECOND EDITION 1998
Published by Construction Marketing Committee, AMERICAN IRON AND STEEL INSTITUTE
In cooperation with and editorial collaboration by STEEL PLATE FABRICATORS ASSOCIATION, INC


Wednesday, May 19, 2010

Generator Selection


Generators must be sized to handle their load based on the continuous KW, kilowatt load, and KVA, kilovoltamp load, and the worst case starting load KW + KVA. They must be derated for temperature and elevation. They are sized also on whether they are continuous or standby use. The following steps are used to obtain information:

Read More


ref:
  • http://www.fs.fed.us/database/acad/elec/greenbook/24_generator_selection.pdf
  • http://www.teachnet.ie/torourke/Physicswebsite/electromagnetism.htm

Monday, May 17, 2010

The using of Electronic Load Controller (ELC) to replace governor in MHP

By Achmad Hasan

The using of Electronic Load Controller (ELC) to replace governor in Microhydro Power Plant (MHP) can hopefully manage the enormous changing of load by giving a quick system response and lower price than governor. Because of providing power for electricity require high cost and the geographic condition of Indonesia also the unbalance spread of load, so the MHP is the most economic energy resource. MHP is the right plant for providing energy especially for remote area with a low load crowd and far from PLN (Indonesian state electricity company) network.

Friday, May 14, 2010

Manning coefficient (n)for several commercial pipes

By European Small Hydropower Association (ESHA)
Over the years many empirical formulae, based on accumulated experience, have been developed. They are, in general, not based on sound physical principles and even, occasionally, lack dimensional coherence, but are intuitively based on the belief that the friction on a closed full pipe is:
1. Independent of the water pressure
2. Linearly proportional to its length
3. Inversely proportional to a certain power of its diameter
4. Proportional to a certain exponent of the water velocity
5. In turbulent flows it is influenced by the wall roughness

One of these formulae, widely used to estimate the flow in open channels, but also applicable to closed pipes, is that developed by Manning
Q= (1/n)* A^(5/3)* S^(1/2)* P^(-2/3)

Where n is the Manning roughness coefficient, P is the wetted perimeter (m), A is cross-sectional area of the pipe (m^2) and S is the hydraulic gradient or head loss by linear meter.
Applying the above formulae to a full closed circular cross section pipe:
S= 10.29 n^2 * Q^2 *D^(-5.333)
S= hf / L (head loss)
hf = Head loss (m)
Q = flow in penstock (m^3/s)
D = inside diameter of penstock (m)
L= lenght of pipe
Manning coefficient n for several commercial pipes


Types of Pipe

        n
Welded steel
Polyethylene(PE)
PVC
Asbestos cement
Ductile iron
Cast iron
Wood-stave(new)
Concrete (steel forms smooth finish)
0.012
0.009
0.009
0.011
0.015
0.014
0.012
0.014

Ref : ESHA (European Small Hydropower Association),”Layman’s Handbook on How To Develop a Small Hydro Site,”2nd ed, 1998. http://www.scribd.com/doc/8885765/Layman-Handbook-for-hydro-electric-power-plants